Hwy 61 Construction…. resurfacing 2012

http://www.dot.state.mn.us/metro/projects/hwy61hugo/

Detours

 

 

Hwy 61 Resurfacing

 

Overview

  • This project will resurface Hwy 61 and replace the traffic signal, at Buffalo Street

 

Location

  • Hwy 61 from Hwy 96 in White Bear Lake to Hwy 97 (210 Street North) in Forest Lake

 

Schedule

  • Construction start: July 9, 2012
  • Construction ends: late - October 2012

 

Cost

  • $4.5 million


This project will replace the roadway surface on about twelve miles of Hwy 61. The new surface should last about 25 to 30 years.

Traffic impacts

Hwy 61 map   

Hwy 61
  • July 27-August 12: Motorists will see no major traffic impacts
  • Week of August 13: Hwy 61 through traffic will be detoured to 35E as crews replace a culvert just north of Meehan Drive. This is the last culvert replacement requiring a detour. The final two culverts will be replaced under traffic Access to local residences and businesses will be maintained. See map for detours details.

 

 

Benefits

  • Resurfacing Hwy 61 under pilot car operation with bituminous to provide a smoother ride,
  • Replacing traffic signal at Buffalo Street and adding aflashing yellow arrow signal to improve safety
  • Replacing six centerline culverts and making additional drainage improvements
  • Installing centerline and shoulder rumble strips to improve safety
  • Relocating signal poles at Headwater Parkway
  • Eliminating the crosswalk across the south side of Hwy 61 approach


Meetings